London: Delays to parliamentary debates on restoring the Palace of Westminster are adding hundreds of millions of pounds to the programme’s cost, officials have warned
According to the AJ’s sister title Construction News, parliamentary clerks spelt out updated financial scenarios in a response to a recent public accounts committee (PAC) report on the Restoration and Renewal Programme (R&R).
Two main options are under consideration: a full decant, with both parliamentary houses moving out for most of the works, previously estimated to cost up to £15.6 billion over 19-24 years; and a phased programme, costing nearly £40 billion over 38-61 years.
But while the R&R programme assumed that parliamentary debates would take place by March 2026, the interim clerks’ report revealed that none had been scheduled as of early November.
‘If debates take place by December 2026, additional costs are between £223 million and £288 million,’ the report said, ‘and if debates take [place] by early/mid 2027, additional costs are more than £479 million.’
The figures include ongoing maintenance costs and the impact of inflation on the overall programme.
The clerks also disclosed new delays to the Commons Building and Infrastructure Portfolio (CBIP), which will provide temporary accommodation for MPs during the works.
The cost forecast for that programme has risen from £2.2 billion to £2.4 billion, which includes inflation, while the planned completion date has been pushed back from 2039 to 2042.
The R&R delivery authority’s analysis of the knock-on effect found that an accommodation shortfall on the Northern Estate could extend completion of the full decant delivery option by ‘approximately five to seven years’, to as late as 2050.
Without mitigation, the clerks estimated that the CBIP delays could add £350 million – £800 million to the full decant option, excluding inflation, compared with the previous range of £280 million-to-£600 million.
Officials described that figure as provisional.
Mitigations under consideration include maximising accommodation within the parliamentary secure line, expanding it to take in nearby government buildings or procuring facilities outside it.
The clerks also identified potential savings of between £576 million and £1.5 billion, excluding inflation, through delivery efficiencies and value engineering.
But they warned the savings ‘could require significant changes to requirements and standards for which the parliamentary appetite for change and any consequential impact on timelines has not been tested’.
The savings will be presented to the R&R programme board in March 2027.
The cost of the House of Lords’ temporary accommodation is also continuing to increase, the clerks warned.
The estimated cost of fitting out the Queen Elizabeth II Conference Centre has risen from £417 million – a figure the PAC branded ‘very high’ in its November report – to £450 million, excluding inflation and VAT.
The authorities said this was largely due to a £10 million increase in net construction cost and the allocation of £20 million of design costs previously funded centrally. This rise will be absorbed within the overall £3 billion of phase one works, they added.
Responding to the clerks, PAC chair Geoffrey Clifton-Brown said that all the options for the programme involve ‘extremely high figures with very big ranges’.
He added: ‘At a time of national fiscal constraint, we would expect the parliamentary authorities to examine these figures extremely carefully to see how they can be reduced before the vote on Phase 2 in 2030.
‘The National Audit Office and the Public Accounts Committee will be scrutinising these costs against progress on an annual basis, [which] would be greatly assisted by the existence of an R&R select committee as we recommend.’
A full response from the clerks to the PAC report is expected in due course.
MPs are set to make a final decision on the project in 2030, following an initial vote on which options to develop further.